docs(references): port style guides, 24 diagram guides, and 9 templates from opencode
All content ported from borealBytes/opencode under Apache-2.0 license with
attribution headers prepended to each file.
- references/markdown_style_guide.md (~733 lines): full markdown formatting,
citation, collapsible sections, emoji, Mermaid integration, and template
selection guide
- references/mermaid_style_guide.md (~458 lines): full Mermaid standards —
emoji set, classDef color palette, accessibility (accTitle/accDescr),
theme neutrality (no %%{init}), and diagram type selection table
- references/diagrams/ (24 files): per-type exemplars, tips, and templates
for all Mermaid diagram types
- templates/ (9 files): PR, issue, kanban, ADR, presentation, how-to,
status report, research paper, project docs
Source: https://github.com/borealBytes/opencode
This commit is contained in:
@@ -0,0 +1,138 @@
|
||||
<!-- Source: https://github.com/borealBytes/opencode | License: Apache-2.0 | Author: Clayton Young / Superior Byte Works, LLC (Boreal Bytes) -->
|
||||
|
||||
# Gantt Chart
|
||||
|
||||
> **Back to [Style Guide](../mermaid_style_guide.md)** — Read the style guide first for emoji, color, and accessibility rules.
|
||||
|
||||
**Syntax keyword:** `gantt`
|
||||
**Best for:** Project timelines, roadmaps, phase planning, milestone tracking, task dependencies
|
||||
**When NOT to use:** Simple chronological events (use [Timeline](timeline.md)), process logic (use [Flowchart](flowchart.md))
|
||||
|
||||
---
|
||||
|
||||
## Exemplar Diagram
|
||||
|
||||
```mermaid
|
||||
gantt
|
||||
accTitle: Q1 Product Launch Roadmap
|
||||
accDescr: Eight-week project timeline across discovery, design, build, and launch phases with milestones for design review and go/no-go decision
|
||||
|
||||
title 🚀 Q1 Product Launch Roadmap
|
||||
dateFormat YYYY-MM-DD
|
||||
axisFormat %b %d
|
||||
|
||||
section 📋 Discovery
|
||||
User research :done, research, 2026-01-05, 7d
|
||||
Competitive analysis :done, compete, 2026-01-05, 5d
|
||||
Requirements doc :done, reqs, after compete, 3d
|
||||
|
||||
section 🎨 Design
|
||||
Wireframes :done, wire, after reqs, 5d
|
||||
Visual design :active, visual, after wire, 7d
|
||||
🏁 Design review :milestone, review, after visual, 0d
|
||||
|
||||
section 🔧 Build
|
||||
Core features :crit, core, after visual, 10d
|
||||
API integration :api, after visual, 8d
|
||||
Testing :test, after core, 5d
|
||||
|
||||
section 🚀 Launch
|
||||
Staging deploy :staging, after test, 3d
|
||||
🏁 Go / no-go :milestone, decision, after staging, 0d
|
||||
Production release :crit, release, after staging, 2d
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Tips
|
||||
|
||||
- Use `section` with emoji prefix to group by phase or team
|
||||
- Mark milestones with `:milestone` and `0d` duration — prefix with 🏁
|
||||
- Status tags: `:done`, `:active`, `:crit` (critical path, highlighted)
|
||||
- Use `after taskId` for dependencies
|
||||
- Keep total timeline **under 3 months** for readability
|
||||
- Use `axisFormat` to control date display (`%b %d` = "Jan 05", `%m/%d` = "01/05")
|
||||
|
||||
---
|
||||
|
||||
## Template
|
||||
|
||||
```mermaid
|
||||
gantt
|
||||
accTitle: Your Title Here
|
||||
accDescr: Describe the timeline scope and key milestones
|
||||
|
||||
title 📋 Your Roadmap Title
|
||||
dateFormat YYYY-MM-DD
|
||||
axisFormat %b %d
|
||||
|
||||
section 📋 Phase 1
|
||||
Task one :done, t1, 2026-01-01, 5d
|
||||
Task two :active, t2, after t1, 3d
|
||||
|
||||
section 🔧 Phase 2
|
||||
Task three :crit, t3, after t2, 7d
|
||||
🏁 Milestone :milestone, m1, after t3, 0d
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Complex Example
|
||||
|
||||
A cross-team platform migration spanning 4 months with 6 sections, 24 tasks, and 3 milestones. Shows dependencies across teams (backend migration blocks frontend migration), critical path items, and the full lifecycle from planning through launch monitoring.
|
||||
|
||||
```mermaid
|
||||
gantt
|
||||
accTitle: Multi-Team Platform Migration Roadmap
|
||||
accDescr: Four-month migration project across planning, backend, frontend, data, QA, and launch teams with cross-team dependencies, critical path items, and three milestone gates
|
||||
|
||||
title 🚀 Platform Migration — Q1/Q2 2026
|
||||
dateFormat YYYY-MM-DD
|
||||
axisFormat %b %d
|
||||
|
||||
section 📋 Planning
|
||||
Kickoff meeting :done, plan1, 2026-01-05, 2d
|
||||
Architecture review :done, plan2, after plan1, 5d
|
||||
Migration plan document :done, plan3, after plan2, 5d
|
||||
Risk assessment :done, plan4, after plan2, 3d
|
||||
🏁 Planning complete :milestone, m_plan, after plan3, 0d
|
||||
|
||||
section 🔧 Backend Team
|
||||
API redesign :crit, be1, after m_plan, 12d
|
||||
Data migration scripts :be2, after m_plan, 10d
|
||||
New service deployment :crit, be3, after be1, 8d
|
||||
Backward compatibility layer :be4, after be1, 6d
|
||||
|
||||
section 🎨 Frontend Team
|
||||
Component library update :fe1, after m_plan, 10d
|
||||
Page migration :crit, fe2, after be3, 12d
|
||||
A/B testing setup :fe3, after fe2, 5d
|
||||
Feature parity validation :fe4, after fe2, 4d
|
||||
|
||||
section 🗄️ Data Team
|
||||
Schema migration :crit, de1, after be2, 8d
|
||||
ETL pipeline update :de2, after de1, 7d
|
||||
Data validation suite :de3, after de2, 5d
|
||||
Rollback scripts :de4, after de1, 4d
|
||||
|
||||
section 🧪 QA Team
|
||||
Test plan creation :qa1, after m_plan, 7d
|
||||
Regression suite :qa2, after be3, 10d
|
||||
Performance testing :crit, qa3, after qa2, 7d
|
||||
UAT coordination :qa4, after qa3, 5d
|
||||
🏁 QA sign-off :milestone, m_qa, after qa4, 0d
|
||||
|
||||
section 🚀 Launch
|
||||
Staging deploy :crit, l1, after m_qa, 3d
|
||||
🏁 Go / no-go decision :milestone, m_go, after l1, 0d
|
||||
Production cutover :crit, l2, after m_go, 2d
|
||||
Post-launch monitoring :l3, after l2, 10d
|
||||
Legacy system decommission :l4, after l3, 5d
|
||||
```
|
||||
|
||||
### Why this works
|
||||
|
||||
- **6 sections map to real teams** — each team sees their workstream at a glance. Cross-team dependencies (frontend waits for backend API, QA waits for backend deploy) are explicit via `after taskId`.
|
||||
- **`:crit` marks the critical path** — the chain of tasks that determines the total project duration. If any critical task slips, the launch date moves. Mermaid highlights these in red.
|
||||
- **3 milestones are decision gates** — Planning Complete, QA Sign-off, and Go/No-Go. These are the points where stakeholders make decisions, not just status updates.
|
||||
- **24 tasks across 4 months** is readable because sections group by team. Without sections, this would be an unreadable wall of bars.
|
||||