All 40 references to borealBytes/opencode updated to the correct source: https://github.com/SuperiorByteWorks-LLC/agent-project Affected files: SKILL.md, all 24 diagram guides, 9 templates, issue and PR docs, plus assets/examples/example-research-report.md (new file). The example report demonstrates full skill usage: flowchart, sequence, timeline, xychart, radar diagrams — all with accTitle/accDescr and classDef colors, no %%{init}. Covers HEK293T CRISPR editing efficiency as a realistic scientific context.
5.7 KiB
5.7 KiB
Gantt Chart
Back to Style Guide — Read the style guide first for emoji, color, and accessibility rules.
Syntax keyword: gantt
Best for: Project timelines, roadmaps, phase planning, milestone tracking, task dependencies
When NOT to use: Simple chronological events (use Timeline), process logic (use Flowchart)
Exemplar Diagram
gantt
accTitle: Q1 Product Launch Roadmap
accDescr: Eight-week project timeline across discovery, design, build, and launch phases with milestones for design review and go/no-go decision
title 🚀 Q1 Product Launch Roadmap
dateFormat YYYY-MM-DD
axisFormat %b %d
section 📋 Discovery
User research :done, research, 2026-01-05, 7d
Competitive analysis :done, compete, 2026-01-05, 5d
Requirements doc :done, reqs, after compete, 3d
section 🎨 Design
Wireframes :done, wire, after reqs, 5d
Visual design :active, visual, after wire, 7d
🏁 Design review :milestone, review, after visual, 0d
section 🔧 Build
Core features :crit, core, after visual, 10d
API integration :api, after visual, 8d
Testing :test, after core, 5d
section 🚀 Launch
Staging deploy :staging, after test, 3d
🏁 Go / no-go :milestone, decision, after staging, 0d
Production release :crit, release, after staging, 2d
Tips
- Use
sectionwith emoji prefix to group by phase or team - Mark milestones with
:milestoneand0dduration — prefix with 🏁 - Status tags:
:done,:active,:crit(critical path, highlighted) - Use
after taskIdfor dependencies - Keep total timeline under 3 months for readability
- Use
axisFormatto control date display (%b %d= "Jan 05",%m/%d= "01/05")
Template
gantt
accTitle: Your Title Here
accDescr: Describe the timeline scope and key milestones
title 📋 Your Roadmap Title
dateFormat YYYY-MM-DD
axisFormat %b %d
section 📋 Phase 1
Task one :done, t1, 2026-01-01, 5d
Task two :active, t2, after t1, 3d
section 🔧 Phase 2
Task three :crit, t3, after t2, 7d
🏁 Milestone :milestone, m1, after t3, 0d
Complex Example
A cross-team platform migration spanning 4 months with 6 sections, 24 tasks, and 3 milestones. Shows dependencies across teams (backend migration blocks frontend migration), critical path items, and the full lifecycle from planning through launch monitoring.
gantt
accTitle: Multi-Team Platform Migration Roadmap
accDescr: Four-month migration project across planning, backend, frontend, data, QA, and launch teams with cross-team dependencies, critical path items, and three milestone gates
title 🚀 Platform Migration — Q1/Q2 2026
dateFormat YYYY-MM-DD
axisFormat %b %d
section 📋 Planning
Kickoff meeting :done, plan1, 2026-01-05, 2d
Architecture review :done, plan2, after plan1, 5d
Migration plan document :done, plan3, after plan2, 5d
Risk assessment :done, plan4, after plan2, 3d
🏁 Planning complete :milestone, m_plan, after plan3, 0d
section 🔧 Backend Team
API redesign :crit, be1, after m_plan, 12d
Data migration scripts :be2, after m_plan, 10d
New service deployment :crit, be3, after be1, 8d
Backward compatibility layer :be4, after be1, 6d
section 🎨 Frontend Team
Component library update :fe1, after m_plan, 10d
Page migration :crit, fe2, after be3, 12d
A/B testing setup :fe3, after fe2, 5d
Feature parity validation :fe4, after fe2, 4d
section 🗄️ Data Team
Schema migration :crit, de1, after be2, 8d
ETL pipeline update :de2, after de1, 7d
Data validation suite :de3, after de2, 5d
Rollback scripts :de4, after de1, 4d
section 🧪 QA Team
Test plan creation :qa1, after m_plan, 7d
Regression suite :qa2, after be3, 10d
Performance testing :crit, qa3, after qa2, 7d
UAT coordination :qa4, after qa3, 5d
🏁 QA sign-off :milestone, m_qa, after qa4, 0d
section 🚀 Launch
Staging deploy :crit, l1, after m_qa, 3d
🏁 Go / no-go decision :milestone, m_go, after l1, 0d
Production cutover :crit, l2, after m_go, 2d
Post-launch monitoring :l3, after l2, 10d
Legacy system decommission :l4, after l3, 5d
Why this works
- 6 sections map to real teams — each team sees their workstream at a glance. Cross-team dependencies (frontend waits for backend API, QA waits for backend deploy) are explicit via
after taskId. :critmarks the critical path — the chain of tasks that determines the total project duration. If any critical task slips, the launch date moves. Mermaid highlights these in red.- 3 milestones are decision gates — Planning Complete, QA Sign-off, and Go/No-Go. These are the points where stakeholders make decisions, not just status updates.
- 24 tasks across 4 months is readable because sections group by team. Without sections, this would be an unreadable wall of bars.