All 40 references to borealBytes/opencode updated to the correct source: https://github.com/SuperiorByteWorks-LLC/agent-project Affected files: SKILL.md, all 24 diagram guides, 9 templates, issue and PR docs, plus assets/examples/example-research-report.md (new file). The example report demonstrates full skill usage: flowchart, sequence, timeline, xychart, radar diagrams — all with accTitle/accDescr and classDef colors, no %%{init}. Covers HEK293T CRISPR editing efficiency as a realistic scientific context.
139 lines
5.7 KiB
Markdown
139 lines
5.7 KiB
Markdown
<!-- Source: https://github.com/SuperiorByteWorks-LLC/agent-project | License: Apache-2.0 | Author: Clayton Young / Superior Byte Works, LLC (Boreal Bytes) -->
|
|
|
|
# Gantt Chart
|
|
|
|
> **Back to [Style Guide](../mermaid_style_guide.md)** — Read the style guide first for emoji, color, and accessibility rules.
|
|
|
|
**Syntax keyword:** `gantt`
|
|
**Best for:** Project timelines, roadmaps, phase planning, milestone tracking, task dependencies
|
|
**When NOT to use:** Simple chronological events (use [Timeline](timeline.md)), process logic (use [Flowchart](flowchart.md))
|
|
|
|
---
|
|
|
|
## Exemplar Diagram
|
|
|
|
```mermaid
|
|
gantt
|
|
accTitle: Q1 Product Launch Roadmap
|
|
accDescr: Eight-week project timeline across discovery, design, build, and launch phases with milestones for design review and go/no-go decision
|
|
|
|
title 🚀 Q1 Product Launch Roadmap
|
|
dateFormat YYYY-MM-DD
|
|
axisFormat %b %d
|
|
|
|
section 📋 Discovery
|
|
User research :done, research, 2026-01-05, 7d
|
|
Competitive analysis :done, compete, 2026-01-05, 5d
|
|
Requirements doc :done, reqs, after compete, 3d
|
|
|
|
section 🎨 Design
|
|
Wireframes :done, wire, after reqs, 5d
|
|
Visual design :active, visual, after wire, 7d
|
|
🏁 Design review :milestone, review, after visual, 0d
|
|
|
|
section 🔧 Build
|
|
Core features :crit, core, after visual, 10d
|
|
API integration :api, after visual, 8d
|
|
Testing :test, after core, 5d
|
|
|
|
section 🚀 Launch
|
|
Staging deploy :staging, after test, 3d
|
|
🏁 Go / no-go :milestone, decision, after staging, 0d
|
|
Production release :crit, release, after staging, 2d
|
|
```
|
|
|
|
---
|
|
|
|
## Tips
|
|
|
|
- Use `section` with emoji prefix to group by phase or team
|
|
- Mark milestones with `:milestone` and `0d` duration — prefix with 🏁
|
|
- Status tags: `:done`, `:active`, `:crit` (critical path, highlighted)
|
|
- Use `after taskId` for dependencies
|
|
- Keep total timeline **under 3 months** for readability
|
|
- Use `axisFormat` to control date display (`%b %d` = "Jan 05", `%m/%d` = "01/05")
|
|
|
|
---
|
|
|
|
## Template
|
|
|
|
```mermaid
|
|
gantt
|
|
accTitle: Your Title Here
|
|
accDescr: Describe the timeline scope and key milestones
|
|
|
|
title 📋 Your Roadmap Title
|
|
dateFormat YYYY-MM-DD
|
|
axisFormat %b %d
|
|
|
|
section 📋 Phase 1
|
|
Task one :done, t1, 2026-01-01, 5d
|
|
Task two :active, t2, after t1, 3d
|
|
|
|
section 🔧 Phase 2
|
|
Task three :crit, t3, after t2, 7d
|
|
🏁 Milestone :milestone, m1, after t3, 0d
|
|
```
|
|
|
|
---
|
|
|
|
## Complex Example
|
|
|
|
A cross-team platform migration spanning 4 months with 6 sections, 24 tasks, and 3 milestones. Shows dependencies across teams (backend migration blocks frontend migration), critical path items, and the full lifecycle from planning through launch monitoring.
|
|
|
|
```mermaid
|
|
gantt
|
|
accTitle: Multi-Team Platform Migration Roadmap
|
|
accDescr: Four-month migration project across planning, backend, frontend, data, QA, and launch teams with cross-team dependencies, critical path items, and three milestone gates
|
|
|
|
title 🚀 Platform Migration — Q1/Q2 2026
|
|
dateFormat YYYY-MM-DD
|
|
axisFormat %b %d
|
|
|
|
section 📋 Planning
|
|
Kickoff meeting :done, plan1, 2026-01-05, 2d
|
|
Architecture review :done, plan2, after plan1, 5d
|
|
Migration plan document :done, plan3, after plan2, 5d
|
|
Risk assessment :done, plan4, after plan2, 3d
|
|
🏁 Planning complete :milestone, m_plan, after plan3, 0d
|
|
|
|
section 🔧 Backend Team
|
|
API redesign :crit, be1, after m_plan, 12d
|
|
Data migration scripts :be2, after m_plan, 10d
|
|
New service deployment :crit, be3, after be1, 8d
|
|
Backward compatibility layer :be4, after be1, 6d
|
|
|
|
section 🎨 Frontend Team
|
|
Component library update :fe1, after m_plan, 10d
|
|
Page migration :crit, fe2, after be3, 12d
|
|
A/B testing setup :fe3, after fe2, 5d
|
|
Feature parity validation :fe4, after fe2, 4d
|
|
|
|
section 🗄️ Data Team
|
|
Schema migration :crit, de1, after be2, 8d
|
|
ETL pipeline update :de2, after de1, 7d
|
|
Data validation suite :de3, after de2, 5d
|
|
Rollback scripts :de4, after de1, 4d
|
|
|
|
section 🧪 QA Team
|
|
Test plan creation :qa1, after m_plan, 7d
|
|
Regression suite :qa2, after be3, 10d
|
|
Performance testing :crit, qa3, after qa2, 7d
|
|
UAT coordination :qa4, after qa3, 5d
|
|
🏁 QA sign-off :milestone, m_qa, after qa4, 0d
|
|
|
|
section 🚀 Launch
|
|
Staging deploy :crit, l1, after m_qa, 3d
|
|
🏁 Go / no-go decision :milestone, m_go, after l1, 0d
|
|
Production cutover :crit, l2, after m_go, 2d
|
|
Post-launch monitoring :l3, after l2, 10d
|
|
Legacy system decommission :l4, after l3, 5d
|
|
```
|
|
|
|
### Why this works
|
|
|
|
- **6 sections map to real teams** — each team sees their workstream at a glance. Cross-team dependencies (frontend waits for backend API, QA waits for backend deploy) are explicit via `after taskId`.
|
|
- **`:crit` marks the critical path** — the chain of tasks that determines the total project duration. If any critical task slips, the launch date moves. Mermaid highlights these in red.
|
|
- **3 milestones are decision gates** — Planning Complete, QA Sign-off, and Go/No-Go. These are the points where stakeholders make decisions, not just status updates.
|
|
- **24 tasks across 4 months** is readable because sections group by team. Without sections, this would be an unreadable wall of bars.
|